4196 FRAXINEWS FARM FRITES 03

We continued the work on an existing installation. Can you briefly outline the project?

“We already had six palletisers with a pallet dispenser that can offer three different types of pallets. In order to produce more pallets per hour, we planned to install a seventh packaging machine in the same space. To keep the production stoppage as short as possible, it was necessary to work in phases. That’s why, in the first phase, the existing pallet dispenser was moved and a lift was installed. This had to be done in a time span of just two days so that production for those six machines could restart. Then, in phase two, the seventh palletiser was built. Finally, in phase three, two additional pallet dispensers with pallet control were installed between the third and fourth palletisers to cope with the additional packaging capacity.”

And how does the palletising process work?

“Cardboard boxes containing bags of potato products are transported at a height in the factory to the palletiser department. While the boxes are being arranged into the first layer in the Qimarox palletiser, an empty pallet is lifted into position. Once a layer is ready, the machine essentially opens up, and the layer of boxes is placed on the pallet. This process continues until a complete tower has been built on the pallet. For the stability of the load, we provide a slip sheet every two to three layers. The stacked pallet is then wrapped and sent to the storage company, also on conveyors supplied by Fraxinus.”

Ok! Now we can delve a little deeper into the project. A critical point in phase one was when production had to be stopped for the relocation of the pallet dispenser.

“Our production runs 24/7, so the palletisers are never idle. However, for this phase we had to stop production, which was a big challenge. We aimed to wrap up the relocation in the shortest possible timeframe, as in our industry, where demand outstrips supply, a production halt is simply not an option. Good preparation was therefore crucial to keep downtime to a minimum. If necessary, we were willing to take drastic action: and so when it emerged that we would save +/- 6 hours if we brought the lift in via the roof with a second crane, we didn't hesitate for a minute.”

Given the continuous production, remote control of the installation is all the more important.

“It's very convenient that switching can be done remotely. We can access the installation software via a network connection and intervene remotely. The cameras that are fitted on the equipment itself are particularly useful, so that we can see if anything is going wrong. That really adds value, because it allows us to find a solution much faster.”

We are talking about a lead time of ten months, which is particularly tight for such an ambitious project.

“We had the first discussions in January and by the end of May we had already started the first phase of the relocation of the pallet dispenser and the construction of the lift. Phase two then took about two weeks, from the construction of the packaging machine to the finishing and testing of the software, the stacking patterns and the stability of the pallets. In October, the additional double pallet dispenser was integrated. There was no alternative: at the same time as this project, the production capacity of one of our production lines was substantially increased, resulting in a higher influx of boxes for palletising. We wouldn’t have been able to handle this with the three existing pallet dispensers, so we really needed those two extra ones.”

Fraxinus was just one of many parties involved in this multidisciplinary project. How did you ensure a smooth process between all partners?

“From adjusting sprinkler pipes and lighting to installing ladders and relocating stairs: many companies had to be in sync. To achieve this we provided a master plan with fixed reference points, to keep it as clear as possible for everyone. The timing was very strict for all parties, but it worked out thanks to a good dose of pragmatism and a can-do attitude from all partners.”

We won't settle for less. Which aspects of our partnership made a lasting impression on you?

“The invoices, those stay with me! (laughs) All joking aside, I can still vividly picture Ruben from Engico (Fraxinus' regular partner) sitting for hours in the cold warehouse, a blanket on his lap, tirelessly programming the software. That image sums up good cooperation, based on a no-nonsense and flexible approach, with a lot of mutual respect.”

That's nice to hear!

4196 FRAXINEWS FARM FRITES 01

Facts & figures

Farm Frites is a Dutch potato processing company. This family business produces more than 80 types of fries, potato products and appetisers and supplies catering entrepreneurs in more than 100 countries around the world.

› Founded in 1971

› 5 production facilities in the Netherlands, Belgium, Poland and Egypt

› 40 sales offices worldwide

› Production: more than 1.5 million tons potatoes per year

› 1,500 employees

More info at www.farmfrites.com

Inspired for your production process?

In need of an optimised production process? We are happy to exchange ideas. Feel free to contact us for an informal meeting.

Let's meet!

This site uses cookies to improve your experience. More info

You are using an outdated browser.

Please update your browser to ensure this website works correctly

Update my browser now!